Estimating Interest Rate Swap Exposure Across Monte Carlo Paths

Article Quant Q&A · Author: Math122

Summary

The document describes how to estimate expected positive exposure (EPE) for an interest rate swap at each date in a Monte Carlo simulation. Once the swap value is known on every simulated path, EPE is the average of the positive parts of those values. If a pricing formula is available, the procedure is direct: apply it to the simulated rates at each date and average the resulting positive exposures.

When no direct pricing formula is available, the swap value can be represented as the conditional expectation of discounted future cash flows. The answer decomposes this value into cash flows arriving before the next grid date and the discounted continuation value at that date. Working backward from maturity, a least-squares regression of discounted next-date values on rate-dependent variables can approximate the conditional expectation, in a way related to the continuation-value step in American option methods. The method depends on suitable regressors and a sound simulation and pricing setup. The document also mentions a swaption-based expression under a particular measure, but does not develop its assumptions or implementation.

Key ideas

  • EPE at a date is the expected positive part of the swap's value at that date.
  • When a pricing formula is available, value the swap on each simulated path and average positive values.
  • Without a direct formula, represent swap value as a conditional expectation of discounted future cash flows.
  • A backward regression can estimate continuation values from discounted values at the next date.
  • Regression quality depends on the chosen rate-related variables and simulation setup.

Tags

Full text
# EPE for interest rate swap


# EPE for interest rate swap












Hey how to calculate Expected positive exposure in the case of interest rate swap? Assume that I simulate $M$ interest rate paths for time grid $0=t_0\le t_1 \le ... \le t_N = T.$ What is the procedure now to calculate value of a swap for each trajectory and each time step using Longstaff-Schwarz LSM? I know that in the case of american option we can go backward but I dont understand how to do it in the case of IR swap. Its easy to calculate cash flows at each time $t_1,...,t_N$ but what next?

## Answer by byouness (score 3, accepted)

https://quant.stackexchange.com/a/63946

#### The expected positive exposure

The expected positive exposure of a swap (or any other type of asset) at a given date $t_i$ is the expectation of the positive part of its value at that date (as that's what you stand to lose if the counterpart defaults, if the value is negative, you lose nothing). This is computed by taking the average over the $M$ paths of your Monte Carlo simulation: $$ EPE(t_i) = \mathbb{E}\left[ \max(V(t_i), 0) \right] \approx \frac{1}{M} \sum_{\omega=1}^M \max(V(t_i, \omega), 0) $$

So, now the question is how to get a grid of your swap values at all paths and dates?

#### Valuing the swap at all Monte Carlo dates and paths

There are two possibilities:

You have a closed-form formula giving you the swap price from your interest rates, which is the case. So, here the procedure is simple and you don't even need LSM:

- at each date $t_i$, you simply take the $M$ simulated interest rates scenarios at that date and plug each one into your formula to get $M$ swap prices;

- you take the average of the positive parts to get the expected positive exposure at that date $t_i$.

You don't have any closed-form formula to price the swap. In this case, you have to remember that the swap's value at each node $(t_i, \omega)$ of your Monte Carlo is in fact a conditional expectation of its discounted future flows under the risk-neutral measure: $$ V(t_i, \omega)= \mathbb{E} \left[ \sum_{t > t_i} D(t_i, t)Flow(t) \mid (t_i, \omega) \right] $$

(by $\mathbb{E} \left[ \ast \mid (t_i, \omega) \right]$ I mean the expectation of $\ast$ conditional on the state of world, in your case the values of interest rates, being the one in your date $t_i$ and path $\omega$)

Remark that the flows falling after $t_{i+1}$ are actually equal to the swap value at $t_{i+1}$ (everything discounted to $t_i$): $$ \sum_{t > t_{i+1}} D(t_i, t)Flow(t) = D(t_i, t_{i+1}) V(t_{i+1}) $$ Leading to this expression: $$ V(t_i, \omega)= \mathbb{E} \left[ \sum_{t_i < t \leq t_{i+1}} D(t_i, t)Flow(t) \mid (t_i, \omega) \right] + \mathbb{E} \left[ D(t_i, t_{i+1}) V(t_{i+1}) \mid (t_i, \omega) \right] $$

The first term is usually straightforward to compute (it falls in the previous section).

For the second term, you can see the similarity to American options, where you need to compute the continuation value, which is a conditional expectations and that you approximate using a LS.

Here, you can approximate this term using a regression of the discounted values of your swap $Y = D(t_i, t_{i+1}) V(t_{i+1})$ on some regressor $X$ depending on your interest rates values (e.g. zero-coupon bond price, annuity, etc.).

By starting from $t_N$ and moving backwards, you will get your swap values on all dates and paths.

## Answer by Felix (score 0)

https://quant.stackexchange.com/a/63934

While I'm not familiar with LSM, the exposure of a swap should be the amount you can lose at any given point in time for your interest rate path.

If you talk about a basic fixed-for-floating swap, I would calculate the value as the difference of a fixed and floating bond. Thus, for the receiver swap: V(swap)= B(fix) - B(fl)

Since you have an interest rate path, you can simply price the bonds according to each time point and with respect to the future interest rate development.

Maybe you find some inspiration here: https://www.mathworks.com/help/fininst/pricing-swing-options-using-the-longstaff-schwartz-method.html

## Answer by Firuz Rahmonov (score 0)

https://quant.stackexchange.com/a/74417

$$ \triangle \ \ \text{EPE}_{\text{swap}} (t) \triangleq E_t^\mathbb{Q} \Big[ \beta(t) \beta(T_k)^{-1} \Big( V_{\text{swap}} (T_k) \Big)^+ \Big] = E_t^\mathbb{Q} \Big[ \underbrace{\beta(t) \beta(T_k)^{-1} A_{k,N}(T_k) }_{A_{k,N}(t) \cdot \frac{\beta(t)}{A_{k,N}(t)} \cdot \frac{A_{k,N}(T_k)}{\beta(T_k)} }[S_{k,N}(t) - c]^+ \Big] = $$ $$ = E^{\mathbb{Q}_{k,N}}_t \Big[ \underbrace{A_{k,N}(t) \cdot (S_{k,N}(t) -c)^+ }_{\text{swaption on swap rate $S_{k,N}(t)$}}\Big] \blacktriangle $$ last element can be calculated using Black-Sholes

Shown in full with attribution under the source's licence. Licence: CC BY-SA 4.0 (Stack Exchange)

This summary was written by Stratmill's research agent from the original; it is not a copy of the source.