The discussion explains why a simulated geometric Brownian motion can have a sample mean far from its theoretical expectation, even when the process uses zero drift and antithetic shocks. With a very large time increment repeated over a long horizon, the terminal distribution becomes extremely dispersed and heavily right-skewed. A small number of unusually large outcomes can dominate the expectation, so the sample average converges slowly and can look misleading across ordinary simulation sizes.
The accepted answer gives the GBM mean and variance and uses the stated parameters to show that terminal variance is enormous after the simulated horizon. It recommends examining uncertainty and using a more reasonable horizon. Other replies recommend smaller time increments to better represent continuous-time dynamics, though the main issue for the stated expectation is the huge horizon and resulting sampling variance. Antithetic paths can reduce variance in some settings but do not remove this heavy-tailed estimation difficulty. The examples are model-specific and do not guarantee quick convergence for other parameters.
Key ideas
- The GBM expectation can remain fixed while terminal variance grows dramatically with the horizon.
- A very long simulated horizon can produce a highly skewed distribution with rare, extreme outcomes.
- Antithetic sampling does not necessarily make a noisy terminal sample mean converge quickly.
- Confidence intervals and the terminal standard deviation help assess simulation error.
- Smaller time increments and a realistic horizon improve the simulation setup, though they address different issues.
Tags
Full text
# Convergence of GBM mean after simulation?
# Convergence of GBM mean after simulation?
As a follow up of my previous question, I am now simulating the GBM step by step for $n$ steps.
I am using the following implementation for the simulation:
$$S_{t+1} = S_t \exp \left[ \left(\mu-\frac{\sigma^2}{2}\right) \Delta t + \sigma \sqrt{\Delta t} Z_t \right], ~ Z_t \sim \mathcal{N}(0,1)$$
Each step represents a unit of time so $\Delta t = 1$.
I use the following MATLAB code:
```
function paths = gbm_exp(mu,vol,s0,nbr_steps,nbr_paths)
shocks = randn(nbr_steps,nbr_paths/2);
shocks_ant = [shocks, -shocks];
paths = zeros(nbr_steps+1,nbr_paths);
paths(1,:) = s0;
for i=1:nbr_paths
for j=1:nbr_steps
paths( j + 1, i ) = paths( j, i ) * exp( (mu - vol^2/2) + vol * shocks_ant( j, i ) );
end
end
```
As you can see, I use antithetic path to try to reduce the overall variance.
The thing is, again, I should have $\mathbb{E}(S_t) = S_0 ~ \forall t$ if I set $\mu=0$.
So I do the following:
```
>> test=gbm_exp(0,.3,100,300,2000);
>> mean(test(end,:))
```
This means that I simulate 300 steps, with $\sigma=0.3$, $\mu=0$ and $S_0 = 100$.
The mean I get though, is something quite small, around 20 on average. So, not at all the excpected 100.
So, I tried increasing my number of paths to 200k and I get a mean of roughly 40 on average.
So I'm suprised by this behavior, I would expect it to converge much more quickly, especially with antithetic paths.
Did I miss something obvious again?
## Answer by Bruno (score 2, accepted)
https://quant.stackexchange.com/a/14628
You should look at confidence interval. Normally, your confidence interval size is proportional to the standard deviation, looking something like: with probability $p$ your value will be in the interval: $$[\bar{S} - k*StdDev, \bar{S} + k*StdDev]$$
Then, getting back to your simulation, we can say that your time step is very big (1 year) and you simulate 300 points, meaning that you simulate outcome in 300 years.
$$\mathbb{E}(S_t) = S_0e^{\mu t} \\ \mathbb{Var}(S_t) = S_0^2e^{2\mu t} (e^{\sigma^2t}-1)$$
In your case, e.g. $\{\mu = 0\}$ we obtain: $$\mathbb{E}(S_t) = S_0 \\ \mathbb{Var}(S_t) = S_0^2(e^{\sigma^2t}-1)$$
Plugging in $\{S_0 = 100, \sigma =.3, t = 300\}$ we obtain: $$\mathbb{E}(S_t) = 100 \\ \mathbb{Var}(S_t) = 100^2(e^{27}-1)$$
I tested similar code with Mathematica (without antithetic) for 300 time steps with 1 year step and got {Paths, Mean, StdDev, {Min, Max}} = {10^6, 60.2203, 16363.3, {2.40216*10^-15, 1.2311*10^7}}. As you can see the standard deviation is very important, it means that your confidence interval will be also big.
Just try to test for 1 year and you should get good average: {Paths, Mean, StdDev, {Min, Max}} = {10^6, 100.028, 30.6978, {22.5584, 370.411}}
## Answer by emcor (score 1)
https://quant.stackexchange.com/a/14631
The GBM is a continuous model, so using large integer time steps naturally leaves large discretization error (which vanishes when you increase the number of steps).
Use small time step 0.001:
```
paths(j + 1,i) = paths(j,i) * exp((mu - vol^2/2)*0.001 + vol * 0.001^0.5*shocks_ant(j,i));
```
Then the mean is almost exactly 100 as expected.
## Answer by Richi Wa (score 0)
https://quant.stackexchange.com/a/14629
appearantly your sampling variance is too large. I reimplemented your example in R. What I first saw is, that the mean got worse if I took more time steps (you take $300$). Your volatility is $0.3$ which is $30\%$ per year and you sample $300$ years. What you should do is the following:
- define a variable ` nbr_steps_peryear`
- choose the number of ` years`
- then you take ` nbr_steps = years*nbr_steps_peryear `
- define a variable ` dt = 1/nbr_steps_peryear `
The `dt` will control your variance. I get nice results with the following set-up:
```
nbr_steps_peryear = 20
years = 5
nbr_steps = years*nbr_steps_peryear
dt = 1/nbr_steps_peryear
nbr_paths = 10^3
S0 = 100
mu = 0.0
vol = 0.3
```
The dt term balances between the drift term $\mu-\sigma^2/2$ and the volatility term.
The main source of the problem is the large number of years - as already mentioned above. With a reasonable number of years and intermediate time steps to balance th drift it should look fine. nbr_steps_peryear = 20 years = 5 nbr_steps = years*nbr_steps_peryear dt = 1/nbr_steps_peryear nbr_paths = 10^3 S0 = 100 mu = 0.0 vol = 0.3
```
shocks <- replicate(nbr_paths/2,rnorm(nbr_steps))
shocks_ant = cbind(shocks,-shocks)
paths = matrix(0,nrow=nbr_steps+1,ncol=nbr_paths)
paths[1,] = S0
for (j in 1:nbr_steps){
paths[j+1,] = paths[j,]*exp((mu-vol^2/2)*dt + vol*sqrt(dt)*shocks_ant[j,])
}
mean(paths[nbr_steps+1,])
summary(paths[nbr_steps+1,])
hist(paths[nbr_steps+1,])
```Shown in full with attribution under the source's licence. Licence: CC BY-SA 4.0 (Stack Exchange)